Adding a new course to an Active Programme

 
Lee Wilkes
Re: Adding a new course to an Active Programme
بواسطة Friday, 5 August 2022, 2:33 AM - Lee Wilkes
مجموعة Partners

Markus

What you are saying is correct. It's even more peculiar if you remove a course from a program. We had a situation where a COVID specific course no longer needed to be part of a program (it was one of 4 courses within the program) - so we wanted to remove it as it didn't matter that some people had completed it. That's fine, but there was no way to reset the program completion, so even learners who had completed all of the 3 remaining courses only showed as being 75% complete (having completed 3 of what was 4 courses), and will only be such.