Date of 1/1/1970 showing in due date of certifications that have not been assigned but not completed

 
Christopher Clewlow
Date of 1/1/1970 showing in due date of certifications that have not been assigned but not completed
by Christopher Clewlow - Tuesday, 10 October 2023, 8:48 AM
 

Good Afternoon,

When we are running reports, the due date column shows the date of 1/1/1970 if the certification does not have a set due date.

This does not look great in the system and suggests to some that our data is incorrect.

Is there a way in the system to make it so the field blanks if no due date is set?

If we go to each cert and set a due date of 3 months after enrolment, will this resolve the issue? What happens if the cert is not completed within the 3 months? With setting a due date, any system behaviours I would need to be aware of?

Thanks,

Chris