Hello

We have a saved report that we wanted to use to update course completions in the last week over in our HR system.

However the report is generating a CSV with data going back to 7 days before the report creation date rather than 7 days from the daily schedule.

When we look at the  report saved settings we get the details set out in the attached image.

Is this a bug or are we missing something please?

Any help greatly appreciated.

William


me
Re: Saved scheduled report
by George Angus - Wednesday, 13 January 2016, 7:11 PM
Group Totara

Hi William,

Can you attach a higher def image? Also can I see your scheduled report settings? 

thanks,

George.

William Ellis
Re: Saved scheduled report
by William Ellis - Friday, 15 January 2016, 6:29 AM
 

Hello George

Sorry about that image I'm a little ashamed!

Anyhoo my colleague found someone identifying the same issue we have in an earlier post

https://totara.community/mod/forum/discuss.php?d=18083#p43327

As we're currently using version 2.6.13 I'm wondering if the bug has been adressed and if so perhaps just updating will amend the issue?

Thanks and Warm Regards

William

William Ellis
Re: Saved scheduled report
by William Ellis - Friday, 15 January 2016, 8:48 AM
 

Hello Again

I've just installed a clean 2.9 Totara site and tested the same report set up with the same outcome.

It looks like this bug hasn't been addressed.

Any suggestions on ways we can collect the last seven days course completions information?

Thanks 

William

me
Re: Saved scheduled report
by George Angus - Tuesday, 19 January 2016, 2:35 PM
Group Totara

Hi William,

Can you tell me exactly how you are setting the report up, and attach a screenshot?